New Marina Store

Pre-memorial day preparation. Most of the store is completed but there are many cosmetic items that will take the rest of the summer.

Welcome inside the new restaurant. We also hired a Chef straight from Maine to enlighten your lake cuisine experience. Look to see new and exciting things from the restaurant.

4/25/2008………… Most of the interior is decorated in vertical slabs of wood. This is the front counter where customers will check out.

4/16/2008………… The store is in place. Check out the new versus the old. The old store is barely visible but its just to the right of the new monster store.

4/16/2008………… A look at the marina in place.

3/27/2008………… A look back from the back of the store. Straight forward is the restaraunt and in front of that will be the cash registers.

3/15/2008………… The new front desk and cash register counter. The new setup will accomodate 2 registers and will speed up all purchase activity.

3/13/2008………… To the right beyond the half wall will be the restaurant. Behind the stairs to the left you can make out some chrome doors in the background. They will be coolers for soft drinks and other cold items. Towards the back by the coolers will house the ice cream and snow cone machines.

3/1/2008…………The 2nd floor patio has railings. All the siding on the store is completed

2/14/2008…………The structure is getting close to completion on the outside

2/8/2008…………Siding installation continues around the building

2/3/2008…………The Roof is completed and the siding is starting its way around the building.

2/1/2008…………Crews started applying the roof with Flat Hollow Marina’s signature color.

1/10/2008…………The picnic tables have been delivered and your welcome to come down and enjoy lunch. This portion of the marina will house the outdoor eating area when finished. Projections are early april for a complete finish.

1/9/2008…………Windows are installed and work on the inside framing has started.

12/30/2007…………Featured here is the overhanging awning for the patio eating area. Support beams are attached to hold the it up temporarily.

12/22/2007…………All truss’s and roof sheeting is complete. If you look closely to the right of the store you can see the 12ft awning for the patio. Most of the covered patio will be foor outdoor eating.

12/22/2007…………Truss’s have been mounted and applying the roof sheeting will begin after christmas. Happy Holidays everyone!!!!!

12/20/2007…………The rooms and kitchen are starting to take shape. The balcony and front patio are being framed.

12/14/2007…………Come on in!!! The walls are up…. just no doors. 

12/12/2007…………Crews are finished pouring concrete and adding sections to the mammoth platform. They have started manufacturing the walls and will soon upright them. The shape of the store will develop soon and will be displayed hopefully on our next update.

Here crews are pouring concrete up on the hill and floating new sections to be added to our monstorous platform that will house the store.

11/07/2007…………….Concrete is poured into a form onto top of styrofoam that will later be covered up.